Float Values Differ between Two Schedules with the only difference being some Asbuilt Activities Deleted
In the Open Standard
Ashley BalesMember for 14 years 7 months
- Created
- 5
- 4
0
On the project I am on, I can only show our Owner specific activities in the schedule as they will not approve a schedule with what my company considers a delay. With this, we escentially have two schedules for our project. Each month we update a schedule and then I copy that schedule, delete out certain asbuilt activities and ensure that the floats are the same. I did a comparison between the two schedules and all the start and finish dates matched for all the activities but the float values were different for some of the activities. How can this be?