Skip to content

P6 - (Activity % Complete) is not getting summarized as compare to other columns.

Ameen PashaMember for 18 years 4 months
Created
5
4
0

Dear Expertise of P6.

With reference to above mentioned subject i.e. P6 - (Activity % Complete) is not getting summarized as compare to other columns. your valuable inputs are required.

Awaiting your usual positive feedback, please consider the snap shot attached herewith for easy refence.

Thanks in advance.

 

. Awaiting  

5 replies

Oldest first
  1. 0
    Ferdinand U. ·

    Hi AmeenActivity % summary

    Hi Ameen

    Activity % summary can be found on the selected percent complete type you assigned for the project (Duration %, Units %), physical % is a different story

    If it is cost loaded, check the performance % and cost % or expense %

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

    3

    .

  2. 0
    Erik Lange ·

    That particular column does

    That particular column does not appear to summarize since it is called "Activity % Complete" as opposed to "% complete".

    If you want the summary you have to choose the percent complete type that you are using (based on duration, cost etc.). So if you are using durations, you need to select the "Duration % Complete" column and that will summarize based on your durations.

  3. 0
    Ameen Pasha ·

    It is Man Hours loaded and

    It is Man Hours loaded and the desired results are coming via Global Change application.

  4. 0
    Deepak Jain ·

    Ameen,Suppose, on a project

    Ameen,

    Suppose, on a project if Design is 20% , Procurement is 10% and Construction is 5%, Would you expect P6 to show you summary % as 35% ? So, There's this logic why P6 doesn't show Activity % at summary level.

    To get overall %, you need to define a common variable among multidisciplinary project activities

    Cheers,

  5. 0
    Mohd Nizam ·

    Ameen,you need to configure

    Ameen,

    you need to configure your performance % complete either you want it to be base on Duration % complete, unit % complete and only performance % complete will show a summary / roll up figures

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?