Is there an add-on for P6 that will create WBS and PERT charts easily such as Critical Tools has built for MS Project.

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Mary,Critical Tools is not

    Hi Mary,

    Critical Tools is not necessary with P6 as its functionnalities already exist in the software:

    PERT Network: display the Activities workspace, then click Activity Network on the toolbar at the top of the screen

    WBS diagram: display the WBS workspace, then click Chart View on the toolbar at the top of the screen

    Alexandre

  2. 0
    Syed Zaidi ·

    Hi, Can you please tell me

    Hi,

    Can you please tell me that how can i calculate Baseline in excel sheet? what are the steps or formula?


    I have an excel sheet that have baseline, then catch-up, then Actual Progress so i am making new sheet so want to know how can i calculate BASELINE?

    Kindly share at kalbe00@hotmail.com


    Thanks,

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?