Activities Relations
In the Open Standard
Jenny IngcoMember for 14 years 9 months
- Created
- 2
- 1
0
Dear Schedulers,
I have WBS and the all activities in it are FS relations so, each one should start dierect behaind the processor is finish. But what happend I have gab now beteen two activities 20 days as far as the relation is FS. So, any idea why that's happinig?
Thank you all
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?