Activities Relations

Jenny IngcoMember for 14 years 9 months
Created
2
1
0

Dear Schedulers,

I have WBS and the all activities in it are FS relations so, each one should start dierect behaind the processor is finish. But what happend I have gab now beteen two activities 20 days as far as the relation is FS. So, any idea why that's happinig?

 

Thank you all

2 replies

Oldest first
  1. 0
    Ronald Winter ·

    Hanson, This gap is probably

    Hanson,

    This gap is probably due to the activity’s calendar.  Look for a vacation period.  Otherwise, look for lag values in the relationships.  Good luck!

  2. 0
    Frederic Fasquelle ·

    Hi Hanson,This gap could also

    Hi Hanson,

    This gap could also be created by some predecessors not marked as "completed" and linked in FS to your current.
    You could also have a look inside your Primavera log report, in chapter "Errors".

    Regards