Exporting & importing to EXCEL

Jaime Sax MaliwatMember for 16 years
Created
1
2
0

I successfully export P6 files to excel,but when I importing back excel to p6 after I load resources,BOQ,cost either the program said out of memory or not responding.I have 25,000 activities in the Project. Your help will be highly appreciated.

1 reply

Oldest first
  1. 0
    Daniel Limson ·

    Hi Jaime,Try doing it in

    Hi Jaime,

    Try doing it in batches, the file must be too big. Note that when importing back to P6, you need the same file or source, when you export to P6, there are actually 2 worksheets created.

    Best regards,

    Daniel