Query on the use of Lags
- Created
- 1
- 2
Greetings,
I am currently preparing a shceule for the installtion of 3 new Chillers and their auxillaries in a Plant Utilities Expansion Project.
I introduced lags in my schedule based on the lead time commitments for procurments by the shortlisted vendors during our preliminary meetings.
If I have Feeder Bucket Procurment with a lead time of 60 days from the date of purchase order, I have assinged a lag of 60 days between the activities "Release PO for Feeder" and " Receive Feeder at Site'.
Both these actvities are on a 5 day per week calender. But the Lag in between these activities also spans the 60 days on a 5 day / week basis.
I want the lag to be on a 7 days/week set up so that by schedule does not refelect 16 extra days over the 2 months of lead time.
What should i do ?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?