Skip to content

remaining units and original duration

Omoba OlawaleMember for 17 years 1 month
Created
1
1
0

 

Could someone please explain what is happening here in P6, Whenever I reduce/increase  my original duration in p6 my remaining units/time remain unchanged. I guess this should be changing with duration

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Victor,look at the Duration

    Victor,

    look at the Duration type field in the AQctivity Detail, General tab: I suppose that it is set to Fixed Units/time

    to change the remaining units/time when you change the activity duration, you should set to Fixed Units

    Alexandre

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?