Regarding the project % completion in Primavera

Krishna Sivachand KodaliMember for 15 years 1 month
Created
3
3
0

Hai Every one,

I findind a problem to get the overall % complete to the project.

i am updating the % progress for each activity in primavera, but i am unable to get the cumulative % progress at each WBS and for project also.

When i am updating the same in MS Project, it is showing the overall % complete.

Can anyone help in this regard,

Thanks in advance.

3 replies

Oldest first
  1. 0
    Ravirg Gehlot ·

    Physical % complete will not

    Physical % complete will not roll up to WBS level u have to use Performance % comp. but ur schedule should be cost loaded ..

  2. 0
    Krishna Sivachand Kodali ·

    Mr. Geholt, Thank you very

    Mr. Geholt,

    Thank you very much fo your reply.

    My project is not cost loaded and i am updating on duration based.

    In that case how to get the rolled progress acheived.

    Thanks in advance.

    Chandu.

  3. 0
    Krishna Sivachand Kodali ·

    Mr. Geholt, Thank you very

    Mr. Geholt,

    Thank you very much fo your reply.

    My project is not cost loaded and i am updating on duration based.

    In that case how to get the rolled progress acheived.

    Thanks in advance.

    Chandu.