P6 Dosn't consider the highest TF

Jenny IngcoMember for 14 years 9 months
Created
2
2
0

Dear All Planners,

Why P6 dosent consider the highest TF in the schedule as the project TF? Seee the example below why P6 not consider teh -67 as the highest TF?

Total   -45

WBS1  -45

WBS2  -67

Thank you for any help,

Regars,

HANSON

2 replies

Oldest first
  1. 0
    Ron Beechey ·

    Hanson Are you really looking

    Hanson

    Are you really looking at a TF or negative 45 and negative 67 and if that is true then -45 is higher than -67 (closer to zero)    Surely you don't have a -67 day total float in your schedule as that is indicating that you would over run your completion date that is showing in the schedule currently by 67 days

     

    Ron

  2. 0
    Jenny Ingco ·

    Got it.. Thanks a lot Ron..

    Got it.. Thanks a lot Ron..