Imported resources set to zero duration

Rob KaneMember for 22 years 9 months
Created
1
3
0
Hi I have just imported some resources , I imported budget cost only. The problem is that all the resource durations have set themselves to zero and dates don't match activity dates. Any ideas on what setting I ma have wrong ? Thanksb Rob

1 reply

Oldest first
  1. 0
    Jenny Ingco ·

    Hi Rob, Did you try to go

    Hi Rob,

    Did you try to go Tools-Level Resources ? If not please, try to do it but, after you make a copy of your schedule and let me know if it's work with you?

     

    Thank you,

     

    HANSON

Log in or join to reply