Global Change to show Days as Month Duration>

Laura VassMember for 14 years 5 months
Created
3
2
0

Hello

Recently moved to high level planning in Months & Quarter duration. Scary as I have come from Hourly Planning!!

I remember from P3 traning years ago that you can create a Global Change, probably with a Text Field Column to show Days into Months? Something like :

Original Duration / 30 = No of Months

 

Can someone tell me the Global Change Data should run in P6 please?

 

Thanks

 

Laura

3 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Laura, Global Change is not

    Laura,

    Global Change is not needed to show durations into Months.

    Go to User Preferences... Time Units... Durations Format.. set Unit of Time to Months

     

    Hope this will help.

     

  2. 0
    Laura Vass ·

    Thanks Raymund for your

    Thanks Raymund for your amazingly quick response.

    I did do that one too.

    You think away to show 2 columns? Months & Days?

  3. 0
    Aldrin Morallos ·

    Hi Laura, Try to provide

    Hi Laura,

     

    Try to provide separate 2 Text Column outside or beside OD column containing "Days" copied from OD & "Months" from there you formulate it using Global Change from Original Duration/30 and you'll see the result.

     

    OD- Original Duration.

     

    Thanks.