Formatting Columns & Opening Multiple Projects

Muhammad FarooqMember for 14 years 4 months
Created
1
2
0

hi everyone,

I am a basic user of P6 and little little issues while working with P6. Two of them given below: -

 

1.    When I add a new column (e.g BL1 Start or BL2 Start or anyone else), It applies to all of my projects, how to get rid of this thing???

 

 

2.    How to work on multiple Projects in P6, like P3. We can switch to other Project through Ctrl+F6 or Window Menu Bar. How to do it in P6??

 

waiting for reply

Thanks & Regards,

 

www.farooq.com@gmail.com

1 reply

Oldest first
  1. 0
    Daniel Limson ·

    Hi Muhammad,There is a P6

    Hi Muhammad,

    There is a P6 feature called "layout" under view. You need to create and save your layouts so that you can recall or restore them anytime without defining your layout all over again.

    regards,

    Daniel