P6 RL8.1 Challenges and Solutions for Discussion

Saeed ShalbafanMember for 16 years 5 months
Created
1
4
0

Dear Colleagues,

Over past year, I have been involved in a mega rail project. I have been a member of program team and we have tried to settle P6 RL8.2 in a governmental organization. There are lots of requests from my client which I seek answers to them through this discussion topics. I do encourage all of you to share your experience in this forum . Thanks in advance.

1- Archive previous layouts/ Files XER.

A Friend in Primavera Admin field advised me that, this can be done by attaching the layouts to the relevant xer files and after exporting , the stand alone xer file would inherit layouts and relevant filters. I have done this practice and after importing those files, there is no sign of layouts or filters. I would like to have your comments on the best way to archive previous files and relevant filters and layouts out of the server.

2- As far as I have understood, P6 RL8.2 uses primavera on the server rather than stand alone like previous versions. Does anybody know what the best backup plan could be if there is a server shutdown?

 

I really appreciate your comments and advice.

 

Regards

 

Saeed

1 reply

Oldest first
  1. 0
    Ravirg Gehlot ·

    Hi , I take a Mannual backup

    Hi , I take a Mannual backup of my PMDB database

Log in or join to reply