Planned percent complete - call for discussion
In the Open Standard
David KellyMember for 21 years 11 months
- Created
- 0
- 3
0
I have many clients who are concerned that "Schedule % complete" is based on the baseline’s duration - whereas they would like it based on "work" or earned value.
I think I have a workaround.
Take a fresh copy of the unprogressed baseline.
Set all activities to "auto compute actuals"
Run Apply Actuals to the current data date.
Demote this version to being a baseline.
The "units % complete" from the baseline IS available - and with the "perfect" progress in the baseline plan, "units % complete" is the expected "performance % complete"
This should constitute "Planned % Complete"
I think I have a workaround.
Take a fresh copy of the unprogressed baseline.
Set all activities to "auto compute actuals"
Run Apply Actuals to the current data date.
Demote this version to being a baseline.
The "units % complete" from the baseline IS available - and with the "perfect" progress in the baseline plan, "units % complete" is the expected "performance % complete"
This should constitute "Planned % Complete"
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?