PM6 level resource
In the Open Standard
Yannick PilonMember for 14 years 9 months
- Created
- 2
- 4
0
Hi,
Can Primavera (P6V7.0) level ident (parent/children) resource? Per example:
Resource level 1: Unit maximum manhours; 50h/h
Resource level 2: Electrician maximum manhours; 20h/h
Resource level 2: Welder maximum manhours; 40h/h
Resource level 2: pipe fitter maximum manhours; 20h/h
As the sum of Resource level 2 (20+40+20=60h/h) is greater than Resource level 1 (50h/h), I want PM6 consider both level. It is possible?
Regards,
Yannick
2 replies
Oldest firstLog in or join to reply