Skip to content

Resource Lag

Ronn Chester BaluyotMember for 18 years 7 months
Created
0
2
0

Hi guys,

How do I put a lag in a specific resource? Example is I have an activity with 10 day duration. A resource will be introduced half-way (after 5 days) up to completion of that activity. In P3 it was very simple. How about in P6?

Thanks.

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?