Martin GomezMember for 16 years 5 months
Created
1
2
0

Hi All

i am wondering if its possible to create progress dropline on Release: 6.2.1. Thanks

1 reply

Oldest first
  1. 0
    Oliver Melling ·

    I dont think this is possible

    I dont think this is possible in Primavera. It kind of goes against the philosophy of the software which is to drive uncompleted work out via the data-date line, thus creating a dynamic schedule.

    Drop-lines were an option in MSP last time i used it.

    HTH