Gantt Bars for non-continuous activities
In the Open Standard
Alfredo VilaMember for 14 years 4 months
- Created
- 2
- 3
0
Dear planners,
I wondering if it is posible to represent Gantt Bars for non-continuous activities using Primavera.
Gantt Bars represent durations, start dates and finish dates of activities in a graphic form, but this is a unique bar per line (per activitie). I mean this bar cannot has two events separately each of one.
For example, I have an activitie named "Field Monitoring" with a week of duration, which has to be doing every month per one year. I don't know how to represent that in P6.
If anybody had an advice, I would be pleased of receive it.
Alfredo
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?