Dear All,

 

How I can use the Global change to change the "At completion total cost" ??

 

Thank you,

 

HANSON

1 reply

Oldest first
  1. 0
    Arend Woltjer ·

    Hi hanson,   at completion

    Hi hanson,

     

    at completion total cost is the sum of at completion expenses, lobor, non-labor and material cost.

    So you have to change 1 of those 4 elements.

    For example like this:

    I hope it answers your question,

    Arend

     

     