Skip to content

Theoric Duration % complete

Marcel FrancesMember for 14 years 3 months
Created
2
2
0

Hi all

Since months ago I have this issue in mind but I did not discover this site till yesterday. It seems there are a lot of pundits here so sure my question will get solved. Here I go.

Let's say that I have an activity in both in the project and in the baseline. This activity was planned to start in the past but it has not started. Hence, the physical % completion is obviously 0. How can I see though the theoric Duration % Complete based on the dates in the baseline?

Thanks in advance,

Frances.

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello Marcel,the "Schedule %

    Hello Marcel,

    the "Schedule % Complete" is the field you need.

    Alexandre

  2. 0
    Marcel Frances ·

    Thanks for your answer

    Thanks for your answer Alexander.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?