Skip to content

Resource Issues when Importing P3 to P6

Mark AllanMember for 15 years 6 months
Created
0
3
0

Hi,

 

I am having issues when importing my P3 plan to P6.  for some reason when I import activities from P3 to P6 neither the budgets or resources are being brought over.  is there a configuration setting in P6 I need to for this to work, or is there something I need to do in P3 to allow this migration etc?

any advice would be much appreciated.

many thanks

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?