Have problem putting in actual in Resource Assignments tab on the left, please help.

Charles CharlesMember for 14 years 3 months
Created
6
4
0

Hi everyone

I was wondering whether I can put in actual in Resource Assignments tab on the left, and i don't want it to split evenly.

For example

Monday 7 Hours

Tuesday 10 hours

Wednesday 3 Hours

 

The actual units in the table just grey out not allowing me to key in anything...:( please help... is there another way of put in actual day to day figure??? please help...

 

 

 

6 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Charles,Create a Finacial

    Charles,

    Create a Finacial Period reference to your distribution interval.

    Key in your actual units per finacial period.

  2. 0
    Charles Charles ·

    Hi RaymundI went to Admin ->

    Hi Raymund

    I went to Admin -> Financial Period -> create the Financial period

    however, where could i find distribution interval? Could you help explaining it more,, please,, 

     

    thank you so much

  3. 0
    Charles Charles ·

    Hi RaymundI went to Admin ->

     

    Hi Raymund

    I went to Admin -> Financial Period -> create the Financial period

    however, where could i find distribution interval? Could you help explaining it more,, please,, 

     

    thank you so much

  4. 0
    Raymund de Laza ·

    Charles,Go to Tools... Store

    Charles,

    Go to Tools... Store Period Performance....

  5. 0
    Charles Charles ·

    I am sorry..i am really new

    I am sorry..i am really new to p6.

    After i store it, then nothing happened... what should i do to be able to update the day to day actual with this function?????

  6. 0
    Charles Charles ·

    ,, so my understanding

    ,, so my understanding is:

    First, I define a financial period then i should be able to enter some actual figures?? then i store it?

    am i right?? where i can put in the actual,,,

     