Mandatory Finish - Longest Path ?!?!?!
In the Open Standard
C. Andre McMillanMember for 14 years 8 months
- Created
- 7
- 2
0
hi.
i have tried to do the following:
creating a Finish Milestone (called FINISH) with a Mandatory Finish with its only Predecessor another Milestone (PROJECTED FINISH). the idea is that the FINISH activity would never fluctuate while the PROJECTED FINISH would show the project Float.
the problem is that it will NOT show the Longest Path except when the project falls behind.
is there a setting or something that could make it work?
thank you.
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?