Original Duration change equal to Remaining Duration???

xadlim B.Member for 14 years 8 months
Created
0
4
0

 

 
Need help please....
 
Why is it that Original Duration in the Summary Level will change equal to Remaining Durationafter I update some activities???
 
Due to this reason my Duration % Complete in the Highest or Project Level will always be 0% since Duration % Complete is computed based in the formula D%= (Original Duration (Current Duration) - Remaining Duration / Original Duration (Current Duration) * 100.
 
 
Thanx for your input.