Remaining units - Primavera
In the Open Standard
Roger HunterMember for 17 years
- Created
- 1
- 2
0
Hi
Looking for some help.
In the schedule I am currently working on , I do not want to record actual units against each activity.
Is there a way in Primavera to make the remaining labour units = estimate to complete labour units?
This would mean as the % complete increases the remaining units automatically decreases.
Hope someone can help
1 reply