Remaining units - Primavera

Roger HunterMember for 17 years
Created
1
2
0
Hi Looking for some help. In the schedule I am currently working on , I do not want to record actual units against each activity. Is there a way in Primavera to make the remaining labour units = estimate to complete labour units? This would mean as the % complete increases the remaining units automatically decreases. Hope someone can help

1 reply

Oldest first
  1. 0
    Oliver Melling ·

    Hi Roger, Look up

    Hi Roger,

    Look up auto-compute actuals in the help...i think this is what you are looking for.

    HTH