Status Update for New Activities Does Not Reflect in Summary Level
In the Open Standard
Kai Pyn TanMember for 15 years 11 months
- Created
- 8
- 3
0
Dear all,
I'm currently using live programme(may add/remove activities follow site situation on monthly update basis) for status update with submission programme as baseline. However when doing statusing, the summary does not capture the performance % complete for new added activity with status.
Then i tried to restore the baseline and reupdate the new added activity, and it does reflect in the summary level
can anyone help on this as i must put the submission programme as baseline?
Regards,
Kai Pyn
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?