Listing Projects That Resources Are Allocated To

Tim ShoesmithMember for 14 years 2 months
Created
1
2
0

Hi,

Im trying to display which Projects each Resource is ultiised on, but cant work out how to do it.

I know you can almost get there by opening each project but I'm trying to display it through the Resources Workspace. 

Anyone got any ideas?

Cheers.

1 reply

Oldest first
  1. 0
    Frederic Fasquelle ·

    Hi Tim,One solution could be

    Hi Tim,

    One solution could be to show it directly on your layout.
    Open "Group and Sort" window and group by "Resources".

    Regards