Earned Labor Units

Henry ChiuMember for 15 years 3 months
Created
3
0

Hi Everyone,

 

Can anybody advise on how to disconnect the duration from the labor units. This is possible in P3 (in options) , how ever in P6 once you change the remaining duration the earned labor units automatically changed. I dont need to change the remaining units as this will affect the S curve. Only the duration is changed not the remaining labor remains the same.

 

Any idea please.

 

Thanks

 

3 replies

Oldest first
  1. 0
    David Craig ·

    Hi Henry,Would changing the

    Hi Henry,

    Would changing the duration type solve this? If you were to change it to something like fixed duration and units, this would keep the units the same, you can change the duration yourself, and only the units/time would change.

    Hope this helps.

    Regards,

    David Craig

  2. 0
    Henry Chiu ·

    Hi David, Thanks for your

    Hi David,

     

    Thanks for your reply

    I already tried this changes,only thing is I need also to update the % complete units in order to determine the current earned units.But then if you change the % complete unitis the duration also automatically changes. I am not sure if there is any equivalent option in P6 like in P3.

     

    Thanks

  3. 0
    Gary Whitehead ·

    Change the "% complete type"

    Change the "% complete type" from "duration", and you should be fine.