Importing Financial Period Actual Units into P6 using a Spraedsheet

Lindsay CameronMember for 14 years 2 months
Created
0
2
0

I want to use Excel to import Actual Units into P6 for Financial Periods.

I have set up Financial periods & a test project. I export data to an Excel Spreadsheet (the Resources Tab), which gives me a template. If there are actual hours in P6, then this comes across into P6.

However, if I update the actual hours in the spreadsheet & then import back into P6, the hours I changed/added do not come across.

 

Has anyone tried this & have a solution?