Modify critical path
In the Open Standard
Marcel FrancesMember for 14 years 3 months
- Created
- 4
- 1
0
Hi all
There is a very big project with its starting date and finishing date. However, I do not want the critical path to go till the end. Along the project there is a milestone which I want to be the end of the critical path. What happens after that milestone can be flexible but the end of the critical path (that milestone) is binding.
If I am to show the critical path for my project, I only want to show critical activities up to that milestone.
What setting would me allow to do that?
Thanks,
Frances.
4 replies