Skip to content

Resource Distribution

Muthukumaru SenthuranMember for 15 years 5 months
Created
1
1
0

Hi Guys,

I want to distribute particular resource throughout the duration of the Activity "A", but when I assigned the resource and generate the report it has been assigned whole resource to the start day of the activity only.

But I created new project and assigned same resource to the another activity , there resource has been distributed through out the duration.

If you have any idea please let me know.

 

Thank you

 

Senthuran

1 reply

Oldest first
  1. 0
    Muthukumaru Senthuran ·

    Thanks Chris I will try

    Thanks Chris I will try

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?