Tracking Gantt Chart in P6

Rafael BolivarMember for 14 years 2 months
Created
3
2
0

I would like to know if it is possible to create a “Tracking Gantt chart” in P6 just like that in MS Project.  If anyone has an idea, I will appreciate it if that person sends me clear instruction or point me to a manual or tutorial.

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Rafael,1. Display the

    Rafael,

    1. Display the "Classic WBS Layaout", then save it as "Tracking Gantt with WBS"

    2. Open the View, Bars dialog and tick the "Primary Baseline" bar; move the bar below the "Critical Remaining Work" bar

    3. Open the View, Columns dialog and select the appropriate columns: Actual Start, Actual Finish, Actual Duration, Remaining Duration, etc... Remove the columns you do not want

    4. Save again the layout

    Alexandre

  2. 0
    Mike Testro ·

    Hi Alexandre Is that like

    Hi Alexandre

    Is that like creating a "Baseline" chart in Asta Powerproject?.

    Best regards

    Mike Testro

  3. 0
    Alexandre Faulx-Briole ·

    Hi Mike,yes, it is;

    Hi Mike,

    yes, it is; definitely!

    Alexandre