Max units per time not matching "Limit" line in recourse usage profile bar chart

Huss PSMember for 4 years 3 months
Created
6
35
0

Hi All,

 

I am using P6 V21.

"Limit" line in "Reosrce usage profile" window it is showing above 50h/d (Max units/time set when adding resource).

Has anyone experience similar issue? What could be the reason? and how to fix it?

 

PS: I tried to upload snapshot but unable to see images or load images on this website. probably becasue it's not https. If i can get help on this as well, that would be great.

Thanks 

6 replies

Oldest first
  1. 0
    David Kelly ·

    Can you double-click on one

    Can you double-click on one of the histogram bars, and report back the figures?

  2. 0
    Huss PS ·

    It's showing 63.

    It's showing 63.

  3. 0
    Huss PS ·

    It's showing 63.

    It's showing 63.

  4. 0
    David Kelly ·

    So, you think the llimit

    So, you think the llimit should be 50, but it is really 63?

     

    Sounds like a Resource Calendar issue

  5. 0
    Huss PS ·

    I checked that again.

    I checked that again. Calender for both activities and resources are same.

    see below snapshot.

  6. 0
    Huss PS ·

    It Worked!!! You were

    It Worked!!! 

    You were correct. 

    I deleted both calenders and added again. 

    Thanks alot.