level of effort activities not updating correct

Kp RaoMember for 15 years 2 months
Created
1
2
0

Hi,

Level of Effort activities taking actual date from the predecessors  but the % complete not updating.

How to get % to LOE activiites.

Urgent help please

kp

1 reply

Oldest first
  1. 0
    Ulkutan Cimen ·

    Select your % Complete Type

    Select your % Complete Type as Duration.

Log in or join to reply