Identifing Duplicate Activities.

Jon GroveMember for 14 years 4 months
Created
1
3
0

I am not sure how it happened, but after importing mulitple xer into my master schedule I have hundreds of duplicate actvities. I need to identify or delete these activities. Any suggestions would be helpfull, going thru the schedule day by day could take awhile. I was hoping that a gobal change or doing a a sort could do it faster. but I just can't wrap my brain around this one.

any help would be appreciated

thanks for your time

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    Jon, Export Activity Details

    Jon,

    Export Activity Details to Excel through SDK... then mark the unnecessary activities with "Y" under the Delete column..

    Import back the file to P6 then you're done.

Log in or join to reply