Skip to content

Cost Data no Importing Properly

Sebastian DiBlasiMember for 15 years 6 months
Created
0
3
0

Contractor has submitted an updated schedule and the cost data (Budget at Completion or Budgeted Cost) for newly added activities is importing incorrectly. The contractor sent me a screenshot of his activities and I can see the correct costs. Yet when I import the file, the costs reset themselves to either $8 or $40. 

I have received numerous other schedules from this particular contractor in the past and have not had this issue. I have received updatse from other contractors and have not had this issue. It leads me to believe that there is a setting or bug somewhere. The contractor is using version 7.0 and I'm using 8.1. Any suggestions would be helpful. 

 

 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?