Activity Relationship

Siva GaneshMember for 14 years 10 months
Created
4
1
0

Hello friends,

I am working on P6 V6.1 and i have done my scheduling process.

The problem is i have assigned relatiionship FS from X activity to Y activity.

Now when i schedule the project with Data date as Z.

The Y activity starts from the Z date eventhough the finish date of X is different.

Hope u understand my issue.

Kindly guide me to solve this problem.

Regrds,

Sivaganesh

4 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Is the finish date of X

    Is the finish date of X earlier than the Data Date of Z?

     

    If so, mark activity Y as "started" in the "Status" tab, and set the correct start date there. (assuming it has actually started. If it has not yet started, then obviously the earliest date it could possibly start would be the data date)

    If not, check for constraints, lags, or other predecessors which may be driving the start date.

  2. 0
    Siva Ganesh ·

    Hi Gary,thanks for your

    Hi Gary,

    thanks for your explanation. but stil am in little confusion.
    I wil explain in an example

    Proj start date - 12 may 2012
    activity 1 - 20 may 2012
    activity 2 - 10 sep 2012
    proj end date - 10 oct 2012

    now if i press F9 and give the 'Data Date' as 10-sep-2012,
    then total schedule changes as

    Proj start date - 10 sep 2012
    activity 1 - 18 sep 2012
    activity 2 - 09 jan 13
    proj end date - 08 feb 13.

    This is the problem. please guide me.

    Regards,
    Sivaganesh

  3. 0
    Gary Whitehead ·

    Sivaganesh,   This is how the

    Sivaganesh,

     

    This is how the data date is meant to work.

     

    You should set the data date to the latest date for which you have a complete set  of progress information.

    If an activity has started or finished, you should check the "started" or "finished" boxes in the Status tab of the activity details screen, and enter the correct start/finish date.

    If you do not do this, Primavera does not know the activity has begun. Any activities that have not begun must by definition get moved to start on or after the new data date.

  4. 0
    Siva Ganesh ·

    Thanks Gary,Now i am clear

    Thanks Gary,

    Now i am clear with my mind.

    Just over confused.

    thanks for your time and clarification.

    Regards,

    Sivaganesh