Actual Date of an activity

Siva GaneshMember for 14 years 10 months
Created
2
2
0

Hello friends,

I have assigned the Actual Date of an activity as 10-july-2012

Now i came to know the activity has not yet started.

When i click the Actual Check box in status. The report comes as,

"Cannot set status to Not Started if activity has actuals"

How can i rectifiy this problem.

Kindly advise.

Regards,
Sivaganesh.

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Set the actuals to

    Set the actuals to zero (resources, cost, etc)

  2. 0
    Kumar Raja ·

    highlight the activity you

    highlight the activity you want to change, go to the status tab, uncheck the finish date, change the physical % complete back to zero, reset the actual & remaining labor units (budgeted quantity)in the labour units box, then you should be able to uncheck the start date, it will ask you Are you sure that you want to change the activity to be Not Started? Jusk click yes and it should work

     

     

    Scott Hastie

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?