Cannot update baseline for in progress activities

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
2
2
0

Hello PPlanners,

I do have a problem with successive baselines: while updating a project, I create a new baseline every month after updating the project

Now some activities are late; say, they will start 2 weeks after the Original Start Date, or finish 4 weeks after the Original Finish Date: Baseline 2, which I have created and assigned after the update, displays correctly for the activities not yet started, B2 Start Date and B2 Finish Date are correct; but the same Baseline 2 still displays Baseline 1 Start and Finish dates for the In Progress Activities

Can somebody explain why?

Thanks, Alexandre

2 replies

Oldest first
  1. 0
    Paul Harris ·

    Have a look at the What

    Have a look at the What Primavera P6 Baseline Bars am I Displaying?  Technical Paper. on my web site.

     

    Paul E Harris

    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
    www.eastwoodharris.com
    www.primavera.com.au - a Primavera scheduling software resources site

  2. 0
    Alexandre Faulx-Briole ·

    Hi Paul,thank you very much,

    Hi Paul,

    thank you very much, your technical papers are very helpfull, as usual

    All the best,

    Alexandre