Resource Summary Report

Duncan PirieMember for 14 years
Created
3
2
0

Hi,

 

relatively new to P6 and want to run a report that is similiar to the Resource Assignment. 

I have grouped my resources into different categories using Resource levels ie. Lvl 1 = Department, Lvl 2 = Department Breakdown, Lvl 3 = resources.

like image below

 

 

What I want to do is produce a report to look the same, however I cannot get the totals to summarise.

See report below

I have tried all sort od Total / Suammry check boxes, but can get this to work.

 

Anyone have any Ideas?

 

Thanks

 

3 replies

Oldest first
  1. 0
    Jean Desjardins ·

    Hi Duncan, An option is to

    Hi Duncan,

    An option is to copy your informations with "Ctrl A" and paste it in an Excel spreadsheet.

    Meanwhile, you will have to format your spreadsheet.

    Jean

  2. 0
    Duncan Pirie ·

    Thanks Jean,I have been

    Thanks Jean,

    I have been copying the reources into excel.  The only thing wrong with that is that it seems to copy the entire project i.e. from start to end date, so end up having to delete all the columns from excel.  Not a major thing, but just thought the report would be easier - If I could get it to work.

    Many Thanks for your reply though.

     

    Duncan

  3. 0
    Toan Nguyen ·

    please snet me native file, i

    please snet me native file, i can do it for you.