Time Units in Primavera P6??

Rajesh PassiMember for 14 years 1 month
Created
3
1
0

Hello Planners!

I had a doubt regarding Time Units in Primavera P6.

What is the difference between Unit Format and Duration Format i have attached the screen shot of that. It would be helpful if explained with short example.
 
Thank you well in advance.

Warm Regards, Rajesh

3 replies

Oldest first
  1. 0
    Jean Desjardins ·

    Rajesh, The units represents

    Rajesh,

    The units represents the level of effort you put on an activity ex : 4 hrs/day or 8 hrs/day.

    It is basically the units that will appears on the invoice and is usually "hour"

    The duration is the elapsed time since the activity was started.

    For axample if you work 4 hrs/day during 5 days you have 20 hours spent (units) and 5 days elapsed (duration)

    Hope this helps.

    Jean

  2. 0
    Rajesh Passi ·

    Hello Jean, Yes! off course

    Hello Jean,

    Yes! off course this example really help me to understand, Jean i had one more doubt can you guide me what is the sequence of scheduling in primavera i want to start a new project i have created EPS,OBS,WBS and added the activities too so then what will be the next step? It would be great help for me Jean.

    Thank you so very much well in advance.

     

    Warm Regards,

     

    Rajesh.

  3. 0
    Jean Desjardins ·

    The next steps would be : -

    The next steps would be :

    - define the relationships between your activities (predecessors and successors)

    - Set the start date of the first activity

    - Set the durations of each activities

Log in or join to reply