Curtain from Calendar

Håkon HaukebøeMember for 14 years 1 month
Created
4
5
0

Hi. I'm new to the forum.

 

I want to create curtains in the bar view based on nonworking months in a calendar. Is that possible.

 

Hawken

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello,you cannot link a

    Hello,

    you cannot link a curtain to a calendar non-working days or months; starting with P6R7, the non-working periods (say: Saturday, Sunday) are shown with a gray zone in the Gantt Chart

    Alexandre

  2. 0
    Paul Harris ·

    Furthermore all non work

    Furthermore all non work periods for all views and all projects in a single database are based on the Default Database calendar and changing this calendar will affect all projects and views. This makes P6 P6 particually difficult when you have a number of projects working on different calendars and each project would like to show their own project calendars as non work periods.

     

     

    Paul E Harris
    Eastwood Harris Pty Ltd
    www.eh.com.au,  www.eastwoodharris.com and www.primatrain.com.au
    Project Control Consultants and Planning and scheduling software book and training manual publishers

  3. 0
    Håkon Haukebøe ·

    Thank you for the

    Thank you for the replies.

     

    Hawken

  4. 0
    Robert Bell ·

    Hi Hawken, You can add them

    Hi Hawken,

     

    You can add them manually and colour code them to for each rescource/calendar/subcontractor etc. Maybe this is will give you what you need?

     

    Rob