Changing Resources on an Activity with Actuals
- Created
- 4
- 2
Morning all!,
I need to clean up a database for my new company (poorly managed for a few years) and I am going through a process for rationalising the calendars and resources to start with.
Calendars has been an easy part but im struggling with the resources...
Basically we now have all manner of variations for the same resource eg;
Welder, welder1, welder-1, welder01 - they are all identical in every way except name.
Ideally id like to global change all those from above to just be "Welder" however in activities with actuals this isnt possible.
I have looked at various ways of doing it from exporting removing actuals then re-importing as new activites etc etc but all seems very time consuming and error prone for the number of projects we have.
Any ideas? they would be much appreciated.
thanks
Chris
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?