Problem with in progress activities
In the Open Standard
Khuram IqbalMember for 13 years 11 months
- Created
- 5
- 2
0
Dear All,
I am new at P6, i am trying to updated the progress of activities but when i run the schedule, i am having problem with all the "in progress" activities.. there is lag after the data date for all of them because of which the "At completion" duration is not equal to the actual duration + remaining duration i cant understand the reason...please note that i updated the schedule using the physical %...............can any one help me in this regard, please, it will be much appreciated.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?