Problem in P6 Resource Usage Spreadsheet and Profile
- Created
- 3
- 1
Hi Guys,
I'm having a problem regarding the resource usage speadsheet and histogram (profile).
I'm experiencing this in my construction program, so i tried it in a one activity program and see if it still exists.
I have an activity with 7 days duration loaded with resource of 70 units linearly distributed. So it means I should have 10 units per day and at the end of the s-curve should have 70 units.
In the spreadsheet, everything is fine and correct. But in the histograme and s-curve it shows only 1 unit (actually it is 1d) and at the end of 7 days the s-curve have 9d. (by the way how to change or remove this "d" units?)
How to correct this problem?
Thanks
3 replies