Problem in P6 Resource Usage Spreadsheet and Profile

Ronn Chester BaluyotMember for 18 years 7 months
Created
3
1
0

Hi Guys,

I'm having a problem regarding the resource usage speadsheet and histogram (profile).

I'm experiencing this in my construction program, so i tried it in a one activity program and see if it still exists.

I have an activity with 7 days duration loaded with resource of 70 units linearly distributed. So it means I should have 10 units per day and at the end of the s-curve should have 70 units.

In the spreadsheet, everything is fine and correct. But in the histograme and s-curve it shows only 1 unit (actually it is 1d) and at the end of 7 days the s-curve have 9d. (by the way how to change or remove this "d" units?)

How to correct this problem?

Thanks

3 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Ronn,Check the setting for

    Ronn,

    Check the setting for Resource Distribution Interval in User Preferences. It should match the Timescale display.

    Unclick the "Show unit label" in the Preferences.

     

     

    Regards,

  2. 0
    Rungsarit Prombrasith ·

    make sure that you didn't

    make sure that you didn't used "calculate average" option

  3. 0
    Ronn Chester Baluyot ·

    Thanks Raymund.

    Thanks Raymund.