Activity codes in P6 for a shopping mall

Carumbaiah KollimadaMember for 15 years 9 months
Created
2
2
0

Hi,

I have recently moved to P6 from MSP and therefore havea only a basic knowledge of P6.

I am preparing a schedule for a massive shopping mall (2basements + 4 shopping floors +2 parking floors) and i wanted to know what level of activity codes need to be defined.

If anyone has worked on a similar project and have a list of defined codes, please share them so that i can get an idea before I start working on my own coding structure

 

Thanks

Carum

2 replies

Oldest first
  1. 0
    Berker Colakoglu ·

    Dear Corum, From my point of

    Dear Corum,

     

    From my point of view code structure may be as follow;

    Phase (assuming it is an EPCT contract and you will include offsite activities aswell)

    Code Value    Description
    ENG    Engineering Phase
    GEN    General Works Phase
    PRC    Procurement Phase
    CNS    Construction Phase
    TCH    Test, Commission& Handover Phase

    Work Group

    Code Value    Description
    C    Civil Works
    G    General Works
    M    Mechanical Works
    E    Electrical Works
    T    Testing/Commissioning/Handing Over Works

    BOQ Division

    Code Value    Description
    DIV02    DIV02 Site Work
    DIV03    DIV03 Concrete
    DIV04    DIV04 Masonry
    DIV05    DIV05 Metals
    DIV06    DIV06 Wood and Plastics

    ... as per your BOQ

    Floor

    Code Value    Description
    GEN    General
    FON    Foundation
    LBF    Lower Basement Floor
    BSF    Basement Floor
    LPF    Lower Parking Floor
    PRF   Parking Floor
    GRF    Ground Floor
    01F    First Floor
    02F    Second Floor
    03F    Third Floor
    RFF    Roof Floor

    ...modify as per your project requirements.

    Zone

    Code Value    Description
    GN    General
    A1    Zone A1
    B1    Zone B1

    ...if it is required to divide building in zones or sections

    Work Item (for all of  your constrcutive activities and also general codes for offsite activities)

    Code Value    Description
    02    Super-Structure
      02.10    Column&Wall&Beam&Slab RC Works
      02.20    Hollowcore Slab Panels
      02.30    Beams,slab& stairs RC Works
      02.40    Topping Concrete

    ....

    Stages for EPCT Phases

    Code Value    Description
    GN    General
    CN    Construction
    SD    Shop Drawing Submittal
    SP    Supplier PQ. Submittal
    SS    Supplier Selection
    AP    Subcontractor Appointment
    MT    Material Submission
    DS    Delivery to Site
    RP    Report Submission

    ....

    You can also add codes such as responsibility,building(if more than one) and various ones as per your project requirements.

     

    Hopefully above descriptions will be helpful for your start.

     

    Regards,

     

    Berker Colakoglu

  2. 0
    Carumbaiah Kollimada ·

    This will be very

    This will be very helpful.

    Thanks a lot Berker

Log in or join to reply