Time Periods

George PapachristouMember for 13 years 10 months
Created
3
1
0

Hello,

I have just started using Primavera P6 and I could use as much advice I could get. Well the problem is that i set an activity duration for 2 days , with working hours 8:00-16:00.What I have seen and do not understand is that while the activity was supposed to start the first day at 8:00 and finish the second day at 16:00, in fact it ends on the third day at 11:00.

Does anybody have an idea why is that happeing and how I can correct it?

 

Thanks,

George

3 replies

Oldest first
  1. 0
    Jose Frade ·

    Most likely the calendar you

    Most likely the calendar you have assigned to the activity does not have the working day starting at 08:00 and finalizing at 16:00. Or the second day is a Holliday ?...in any case check calendar of thee activity or the calendar of the resource if any.

     

     

    BR

    JMFrade

  2. 0
    Jose Frade ·

    .

    .

  3. 0
    Jose Frade ·

    second

    second