Original/Remaining Duration

Burak HANMember for 13 years 10 months
Created
2
1
0

Hello,

    I am using Primavera P6 for project management. I have a situation which I see as a problem for myself. If someone explains this to me, it will be really better for my management.

    The situation is that; I am entering the the start and finish date for an activity. ( The activity is started so I am checking the started box). Then I am putting a "finish on" constrain to the activity. (The same date as finish date). After that, I am scheduling and I see "negative total float". I want my activity to finish on date which I assigned as "finish on date". However, the program is taking the finish date for a forward date and it shows me negative float. 

     I see that the activity has the same original and remaining date, that's why I have the negative total float. Because my scheduling time is after the start date. But I want to make the constraint and finish the activity on finish date.

    Any help?

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Best Practise

    Best Practise Solution:

    Remove the "finish on" constraints, and instead adjust the Remaining Duration to get the correct forecast finish dates

     

    Poor Practise (but quicker) Solution:

    Remove the "finish on" constraints, and instead use "expected finish" dates

  2. 0
    Burak HAN ·

    Thank you Gary,

    Thank you Gary,

         