Resource Levelling in P6
- Created
- 6
- 3
Hi Everyone,
I am levelling the resource in P6 but I dont know if it is correct one or not. Let me explain.
I am looking at the "Resource usage profile" and I see that in some remaining columns, there are overallocated units. Then, I am clicking on levelling button and nothing is changing. (I am not preservingearly and late dates and I am leveling just this activity.) After then, I am changing the finish date manually to a further date and I am clicking on the levelling button again. The result that I am able to level the resource by this way manually.
Do you think that I am levelling correctly?
6 replies
Oldest firstLog in or join to reply