Skip to content

Schedule percent complete

Naseer YamaMember for 14 years 2 months
Created
3
2

3 replies

Oldest first
  1. 0
    Irfan Khan ·

    welcome Naseer,the Schedule

    welcome Naseer,

    the Schedule percent complete is equal to your planned progress.

     

    regards,,,,

  2. 0
    Andrew Tan ·

    Hi,I believe,Schedule percent

    Hi,

    I believe,

    Schedule percent complete is based on planned progress which is your baseline.

    If you want to compare baseline and current schedule, this should work.

     

    Thanks,

  3. 0
    Omid Khan ·

    it is the planned progress

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?